← Products

SL235-STD-GRY

SuperSleeper - 60*205*2350mm - Grey
Henan Zhongsheng Composite Material Co. LtdMould HZ-SL-2352.35 m longretailSL235-STD-GRY-PK (144)
On hand
2,857
loose units (packs rolled up)
On order
18,941
open POs in transit
Safety floor
2,986
z × σ over lead time
Avg forecast
4,289
units / month over horizon
Demand forecast
units / month · shape from history, level from target
4,8689,736Jul 26Aug 26Sep 26Oct 26Nov 26Dec 26Jan 27Feb 27Mar 27Apr 27May 27Jun 27
Projected inventory
closing stock vs safety floor · ▲ container arrives
7,71115,422safety floor 2,986Jul 26Aug 26Sep 26Oct 26Nov 26Dec 26Jan 27Feb 27Mar 27Apr 27May 27Jun 27
Incoming POs arrival dates derived — override when a supplier reports a delay
PO-00000142 placed 3 Feb 2026
1,296 units
lands 10 Jul 2026 · derived from lead time + blackouts
PO-00000145 placed 12 Feb 2026
576 units
lands 10 Jul 2026 · derived from lead time + blackouts
PO-00000150 placed 5 Mar 2026
2,880 units
lands 13 Jul 2026 · derived from lead time + blackouts
PO-00000151 placed 5 Mar 2026
1,728 units
lands 13 Jul 2026 · derived from lead time + blackouts
PO-00000152 placed 5 Mar 2026
144 units
lands 30 Jul 2026 · derived from lead time + blackouts
PO-00000153 placed 9 Mar 2026
576 units
lands 25 Jul 2026 · derived from lead time + blackouts
PO-00000154 placed 12 Mar 2026
576 units
lands 30 Jul 2026 · derived from lead time + blackouts
PO-00000162 placed 30 Mar 2026
1,834 units
lands 10 Jul 2026 · derived from lead time + blackouts
PO-00000165 placed 12 Apr 2026
261 units
lands 13 Aug 2026 · derived from lead time + blackouts
PO-00000166 placed 13 Apr 2026
576 units
lands 16 Aug 2026 · derived from lead time + blackouts
PO-00000168 placed 28 Apr 2026
1,152 units
lands 2 Aug 2026 · derived from lead time + blackouts
PO-00000169 placed 28 Apr 2026
576 units
lands 5 Aug 2026 · derived from lead time + blackouts
PO-00000170 placed 11 May 2026
604 units
lands 7 Aug 2026 · derived from lead time + blackouts
PO-00000171 placed 12 May 2026
1,008 units
lands 5 Aug 2026 · derived from lead time + blackouts
PO-00000172 placed 31 May 2026
604 units
lands 8 Aug 2026 · derived from lead time + blackouts
PO-00000173 placed 1 Jun 2026
540 units
lands 15 Aug 2026 · derived from lead time + blackouts
PO-00000174 placed 2 Jun 2026
251 units
lands 18 Aug 2026 · derived from lead time + blackouts
PO-00000175 placed 7 Jun 2026
1,545 units
lands 19 Aug 2026 · derived from lead time + blackouts
PO-00000176 placed 9 Jun 2026
846 units
lands 22 Aug 2026 · derived from lead time + blackouts
PO-00000177 placed 10 Jun 2026
864 units
lands 25 Aug 2026 · derived from lead time + blackouts
PO-00000179 placed 11 Jun 2026
504 units
lands 2 Aug 2026 · derived from lead time + blackouts
Constraints shaping this plan
MouldHZ-SL-235
Dedicated tooling; batches round to full runs.
ManufacturerHenan Zhongsheng Composite Material Co. Ltd · Henan, China
4 wk manufacture + 4 wk transit — orders land ≈1.8 months after placement.
Minimum order0 units (run 0)
Quantities round up to full runs; MOQ applies to the whole mould run.
Container footprint0.024 m³ · 5.4 kg per unit
Drives container fill (volume + weight). Source: weight:pack / volume:pack.
Unit cost $15.30 AUD — manufactured / ex-factory (72.85 CNY · Henan Zhongsheng Composite Material Co. Ltd). Landed cost is a later phase.
Planning config
User-owned — ERP fields above are read-only. Changes take effect on the next run.
Container packing needs no per-product config — weight & volume are read from the ERP (with fallbacks) and shown under “Constraints shaping this plan”.